|
Buildings
Garage Mahal: University of Houston Ramps Up
(texas.construction.com,
August 2006 issue)
By Lesley Hensell
 |
 |
| The northwest corner
elevation at night. |
Not all parking garages are created
equal. Especially at the University of Houston, where a new
mixed-use parking structure, with its complex construction
scheme, will offer plenty of parking space as well as finished-out
areas dedicated to retail and academics when it reaches final
completion this month.
Built on an existing surface parking
lot at Calhoun Road and University Drive, the $25.8 million
garage encompasses 519,000 sq. ft. over five levels. It provides
1,500 parking spaces, as well as a 25,000-sq.-ft. academic
and welcome center and 10,000 sq. ft. for retail use on the
building's first floor.
The garage is a "mixed-use structure
that will help to enhance campus life," said Dave Irvin,
associate vice chancellor and associate vice president for
facilities and plan operations at the University of Houston.
"There will be great synergy with all parts of the building
- retail, the visitors' center and the academic center. Visitors
will be able to buy tickets for different events on campus,
while prospective students and parents will be able to learn
more about admissions and financial aid."
The garage relies on express ramps,
which raised the degree of difficulty for its design and construction.
"With this design, there are flat
decks with an express ramp at one end," said Matt Elliott,
project manager for SpawGlass of Houston, the general contractor.
"This creates a more efficient flow of traffic and a
larger area of flat deck. The flat deck is attractive from
a constructability standpoint, but the express ramp is pretty
complicated."
Unlike regular ramps in garage designs,
express ramps are intersected by deck columns at different
heights on different levels of the structure. As a result,
it was more difficult to design, form, reinforce and place
the columns, Elliott said.
"The express ramp design has several
advantages," Irvin said. "First, it allows a clear
view of every floor of the garage, which is key to enhancing
security. Also, our master plan is to expand the garage in
the future. With this design, we can simply add more flat
parking space on the other side of the ramp using a single
ramp to quickly load the entire garage."
 |
 |
| Coordination and
scheduling in the heart of a large, active university
area meant pours were scheduled beginning at 1:00 a.m.
|
Work on the fast-track project launched
in January 2005, and the parking portion of the facility opened
just 12 months later - ahead of schedule and just in time for
the spring semester. To accomplish this, the SpawGlass team
set up an aggressive pour schedule for the garage's cast-in-place
concrete structure. Each of the garage's 109,000-sq.-ft. decks
was split into five sections of approximately 25,000 sq. ft.
each.
"To cycle the formwork properly
and meet the schedule, we created a 25-week pour schedule,"
Elliott said. "In most cases, we worked after-hours for
the formwork and reinforcing placement. All concrete placements
were started at 1 a.m. on a Friday morning."
This late-night schedule helped the
team work effectively in a congested university environment
by allowing concrete staging, off-loading and clean-out at
less-active times.
"By Monday morning at 7 a.m., the
cylinders were broken at the testing lab," Elliot added.
"That gave us the rest of the week to wreck the formwork
and move on to the next two areas to get ready for the next
Friday-morning pour."
To ensure that there was enough time
to move on to the next area, the team invested in a premium
4,000 psi mix that guaranteed a 3,000 psi break within three
days. That way, the team could start stressing post-tensioned
cable within three days.
"A couple of times, to speed things
up, the lab broke cylinders on Sunday mornings," Elliott
said. "We did end up working quite a few weekends."
As the team worked through concrete
pours, project managers took extra care to document the locations
of post-tensioned cables, which became particularly important
as work began on the finish-out of the first-level indoor
spaces, Elliott said.
"Since the finished spaces are
on the first level, we knew there would be a lot of equipment
and materials hanging from the deck above," he said.
"Since it is full of post-tension cables, there was a
big concern that one of these cables could be ruptured when
subcontractors went to anchor a piece of equipment in the
deck above.
"We went to great lengths to identify
cables so that, when we started building out below, it would
be easy to know exactly what was going on."
For the columns on the project, SpawGlass
chose white Portland cement for its lighter color. But the
quick-setting nature of the cement required tweaks to forming
and placement techniques.
"That mix in and of itself is kind
of volatile, so we had to play with it to keep it workable
long enough to pour the columns and make them look good,"
Elliott said.
In addition to more convenience, the
parking garage will offer additional security to students
and staff. Administrators have installed video cameras and
blue-light security phones throughout the garage, and a University
of Houston police officer is stationed at the building. The
lighting is nearly twice that in an average garage.
Nestled among oak trees, the garage
was designed to aesthetically match other campus buildings.
It features a skin of face brick, glazed tile and cast stone.
"Inside and out, the garage was
built to be much more than simply a place to park," Elliott
said. "It truly enhances the campus around it."
Key
Players
Owner:
The University of Houston System, Houston
Construction Manager
at Risk/General Contractor: SpawGlass, Houston
Architect:
STOA/Goleman/Bolullo Architects, Houston
Structural Engineers:
CBM Engineers Inc., Houston
MEP Engineers:
Infrastructure Associates Inc., Houston
Civil Engineers: Jaymark Engineering Corp., Houston
Reinforcing: Texas
Cold Finished Steel Inc., Houston; Suncoast Post-Tension,
Houston
Reinforcing Placement:
Doran Steel Inc., Houston
Concrete Materials:
Transit Mix Concrete & Materials Co.,Beaumont
Concrete Placement:
Alpha Delta Concrete, Houston
Masonry: Camarata
Masonry Systems,Houston
Curtain Wall:
Floyd's Glass Co., Houston |
|