|
Hierarchical
Structure Introduces Logic to Randomness
Legs, trusses
and layers of secondary members shape Beijing stadium's bird's nest
10/23/2006
By
Janice L. Tuchman and Andrea Ding-Kemp

 |
 |
| The
client wanted a dramatic building that would make a statement
and seat 91,000 for the opening and closing ceremonies of the
2008 Olympic Games in Beijing.
Photo: MichaelGoodman/ENR |
When the Olympic torch arrives in Beijing
for the opening ceremonies of the 2008 Summer Olympics, the setting
for the thousands of athletes, dignitaries and spectators will be
a stadium that is structurally innovative, architecturally international
and culturally Chinese. Swiss architect Herzog & de Meuron,
collaborating with avant-garde Chinese artist Ai Weiwei, took inspiration
from the auspicious natural form of a bird's nest. Façade
and structure are identical, and structural elements "mutually
support each other and converge into a grid-like formationalmost
like a bird's nest with its interwoven twigs,the firm says.
The functional and technical requirements
of an Olympic stadium are strenuous. The Beijing venue, which will
be used for opening and closing ceremonies and track and field events,
will have 80,000 fixed seats and 11,000 temporary seats. Elliptical
in plan, the seven-level stadium will have 258,000-sq-meters of
gross floor area. The 330 x 220-m roof will be saddle-shaped, and
the surface of the 69-m-tall facade inclines out by about 13°.
 |
 |
| Image: Herzog &
de Meuron |
The architect teamed with ArupSport for multidisciplinary
engineering services and sports architecture consulting. "Clearly,
the client wanted an iconic statement, a dramatic and exciting building,says
J Parrish, architectural director for ArupSport. Arup had worked
with the Basel, Switzerland-based architect on Munich's Allianz
Arena, scene of the 2006 World Cup. Herzog & de Meuron, ArupSport
and China Architectural Design & Research Group won the international
design competition for the job held by the Beijing Municipal Planning
Commission in 2002. "We designed from the inside out, using
a combination of CATIA and purpose-designed software,Parrish adds.
The team also gave a lot of consideration to "legacy uses"how
the stadium would function after the Olympics are over. A hotel
is being built into the complex, for example, along with two levels
of commercial development that will open after the games.
 |
 |
Fabricating
and erecting the frames was a challenge for contractors.
Photo: MichaelGoodman/ENR |
Martin Simpson, the lead structural engineer
on the initial phases who is based in Arup's Manchester, England,
office, says the structure is less random than it looks. The Beijing
stadium has a "hierarchical structure of primary, secondary
and tertiary members. The primary structure has a series of legs
and trusses plus layers of secondary members that create the random
appearance. The eye is drawn to the massing, not to the layers.
It's a way of introducing logic to randomness,Simpson says.
The primary system has 24 column points. The
roof, which springs from the columns points, is a free span of the
bowl. The original design had a roof that opened and closed, but
as costs came under scrutiny, the design team came up with a fixed-roof
alternative, which increased the size of the opening but kept the
roof frame as a single plate. "It lowered steel weight and
produced a savings of about 10% on costs,Simpson estimates. No official
cost figures on the stadium have been released, but published estimates
put the cost at about $423 million after the redesign.
 |
 |
| Beijing's pollution is prompting
the team to install roof membrane closer to the Olympics. Photo:
AP |
Plates 1.2 meters wide are used to build up
the box sections. The plates are 10 to 100 mm thick, depending on
the forces at a particular location. "The plate thicknesses
were optimized to cope with the structural loads, including earthquakes,said
Michael Kwok, director of Arup Hong Kong and National Stadium project
director. The seismic design includes three different load casesfor
2000-year, 475-year and 50-year earthquakes. There are different
levels of performance criteria so the structure will remain elastic
and withstand shaking.
Building the Nest
National Stadium's main contractor is Beijing
Urban Construction Co. Ltd., and one of the firm's senior engineers
reviewed progress with ENR. Work started at the end of 2003, driving
piles up to 37 m deep and up to 1.2 m in diameter. There was a pause
for several months in 2004 while the modifications were made to
eliminate the retractable roof and enlarge the roof opening.
 |
 |
| Steel plates for the box sections
vary in thickness according to the forces at the location. Photo:Michael
Goodman |
By November 2005, cast-in-place concrete work
for the seating bowl structure was completed. Precast concrete seating
tiers will be installed. The precast work is being done at Beijing
Urban Construction's own precast yard.
Erection of the structural steel columns began
at the end of 2005 by Shanghai Baoye Construction Corp. and Beijing
Urban Construction Jinggang Steel Structure. "Fabrication of
the welded steel frames was not easy, and connecting a structure
with 180 openings was a tough job," according to the contractor.
The 180 sections were welded together to connect the main structure,
which was finished by the end of August. A total of about 40,000
tonnes of steel was erected, which required 20,000 drawings to detail
the twisting, turning frames. On Sept. 17, workers unloaded the
structure from its temporary supports, and the main structure was
complete.
 |
 |
| Main
structure was unloaded from its temporary supports in September.
Photo: AP |
Finishing Touches
Mechanical systems are now being installed,
and the entire stadium is scheduled for completion at the end of
2007. Also ahead is the installation of roof claddingabout
40,000 sq m of ETFE (ethylene tetra fluoroethylene) panels on the
upper surface. An inner acoustic membrane made of 50,000 sq m of
Tef-lon fabric will be installed to absorb sound.
A joint venture of Covertex and Beijing N&L
Fabric Technology Co. Ltd. is fabricating and erecting the membranes.
The outer membrane will be attached to a secondary structure along
the roof opening using L-shaped angles welded to the steel beams
to form a channel to carry water runoff. With Beijing's well-known
pollution problems, contractors are holding off until the middle
of 2007 to install the membrane so that it will still be clean and
pretty for the Olympics.
|