|
Final
Height of 'On-Deck' Tallest Tower Shrouded in Secrecy
But residential
concrete frame, with short spans, makes it easier to exceed 700
11/06/2006
By Peter Reina in Dubai with Nadine Post

 |
 |
Concrete
pumps must reach 550 m.
Photo: MichaelGoodman/ENR |
Speculation among supertall-building pundits
once had the $1.1-billion Burj Dubai rising 800 meters or more.
Currently, the developer admits to only 700-plus. The towers
architect-engineer is sworn to say only 600-m-plus. And the main
contractor claims not to know the final height.
The secret gets harder to keep as the tower,
now at about 80 stories, rises toward its pinnacle, at an average
of one floor every three days. Whatever its final stopping point,
Burj Dubai is on course to supersede the world record holder, the
509-m-tall Taipei 101, by summer, says Greg Sang, assistant director
for projects at local owner Emaar Properties PJSC.
The largely residential and hotel burjArabic
for toweralready surpasses Europes tallest building,
Moscows 264-m Triumph-Palace. Located just south of the United
Arab Emirate city, the iconic centerpiece of Emaars $20-billion
Burj Dubai Down- town mixed development, is taking the form of a
tapering, three-winged tower, mainly of over 280,000 cu m of concrete
rising 162 floors. From level 156, the tower will be framed with
some 0.5 million tonnes of structural steel in equipment floors
and the spire.
 |
 |
Top steel structure (model, below)
may be about 200 m tall. Concrete setbacks help fool wind.
Photo: MichaelGoodman/ENR
|
The steel frame alone will be almost
as tall as the U.K.s tallest building at Londons
Canary Wharf, which is 225 m, says Rob Pickering, project director
of Hyder Consulting Middle East Ltd., the towers construction
supervisor and designer of record.
The
reinforced concrete structure serves the quest for height of Emaar,
which is a third owned by Dubais ruling family. But it meant
taking wind engineering to new heights. We virtually designed
[the tower] in a wind tunnel, says Bill Baker, structural
partner at architect-engineer Skidmore, Owings & Merrill LLP,
Chicago. In the old days, wind tunnels were for confirmation
of forces, not to tell you what the building would look like.
Adds Anton Davies, a director of Burj Dubais
wind consultant, Rowan Williams Davies & Irwin Inc. (RWDI),
Guelph, Ontario: We probably did a million dollars worth of
work on this.
The largely residential towers smaller
room sizes allowed greater use of structural walls than would have
been possible for an office building, notes Eric Tomich, SOMs
associate partner on site. Having designed a broadly similar structure
for Koreas 264-m-tall Tower Palace III a few years ago, Baker
says we knew we could get this structural system pretty damn
high. Essentially, every piece of vertical concrete is part of the
lateral system.
Stiff Core
The stiff, six-sided core will reduce twisting
to below residents discomfort threshold. Lateral stability
comes from pairs of roughly 60-centimeter-thick, reinforced concrete
shear walls forming central corridors of the three symmetrically
distributed wings.
Lower wings, which project over 60 m from
the core, shorten in turn by 9-m bays creating 27 setbacks spiralling
up the tower. Perimeter columns, generally 1.9 m in diameter, support
outermost bays.
 |
 |
| Baker. |
The constantly changing profile may complicate
construction but it prevents the building from resonating to wind-induced
vibrations. Vortex shedding is going to happen, but you dont
want it organized, says Baker.
Shear walls at the towers two-floor-
deep mechanical levels act as outriggers. The four levels of complete
outriggers, and one partial, mobilize all vertical elements to resist
lateral loads.
 |
 |
 |
|
Irwin
(left) used 1:50 scale for wind tunnel model of top of tower.
Photo: NRC Canada |
Tower
was virtually designed in wind tunnel, says engineer.
Photo: SOM |
 |
 |
Wind consultant RWDI worked with SOM during
design to refine the shape and orientation. Using local and regional
wind data, RWDI proved the original 45-m-per-sec design wind speed
would be excessive. Based on the data, authorities allowed a design
wind speed over 15% lower than the value set by their interpretation
of the local code, says Peter Irwin, RWDIs president. Otherwise,
it would certainly have been a much more expensive structure,
adds Baker.
For detailed analysis, numerous tunnel tests
were run, first on simple force balance models. Tests on designs
using full aeroelastic models gave the ultimate in precision,
says Irwin. Special tests on a 1:50 model of the tower top proved
previous work to be free of scale effects, he adds.
Because of the height, RWDI used weather forecasting
software to assess structural effects of the regional Shamal wind
that can cause unusual profiles of...speed with height,
says Irwin.
For the burjs higher levels, RWDI had
only one source of balloon datafrom Abu Dhabi. We were
missing information and used MM5 [weather software] to help fill
in gaps and to extrapolate to Dubai, adds Irwin.
RWDI revealed the occurrence of high-speed
Shamal winds during night time temperature inversions between 300
m and 500 m above ground. But their structural effect was secondary
to ordinary wind loads higher up, says Irwin. Even at 700 m, the
tower needs no mechanical damping, though there will be space left
for some.
The burj, which started off to be the worlds
tallest, grew as tests revealed the structures inherent ability
to satisfy Emaars desire for ever greater height as a selling
point. The strategy workedthe tower is pretty much sold
out, says Sang.
For statutory requirements no one code applies.
SOM used the (U.S.) International Building Code overlain with the
(U.S.) National Fire Protection Associations code for fire
and emergency escape. And it adopted British standards for fire
detection and alarm systems. Among safety enhancements
the building includes air-conditioned, pressurized refuge areas
at four levels, connected by corridors to stairs of other wings.
No Experiments
Environmentally, we havent exploited
a lot of experimental technology, partly because of the scale,
says SOMs Tomich. Rather than harness Dubais abundant
solar energy, the design aims to cut power demand. With the areas
extreme heat, the biggest problem for energy consumption is cooling.
Heat gain will be cut by different coatings on both layers of the
twin-leaf curtain walls. One will reflect daytime solar heat and
the other will block long-wave radiation during hot nights.
In 2003, within weeks of winning a limited
design competition, SOM started work. Also in 2003, for project
management, Emaar hired New York City-based Turner International,
a subsidiary of Turner Construction Corp., Dallas. This year, Emaar
and Turner Corp. announced a new entity, Turner International Middle
East Ltd., to jointly pursue projects in the Gulf.
To work out the burjs constructibility,
SOM and Hyder involved Turner very early in the design. The design
is based on high-strength concrete, with most of of the towers
vertical concrete rated at 80 mpa and the rest at 50 mpa. In Dubai,
they had produced 80 mpa only in the last four to five years, says
David Bradford, Turners construction manager.
 |
 |
Work
continues around the clock to keep schedule and take advantage
of cooler evenings in extremely hot climate.
Photo: MichaelGoodman/ENR |
Because of the structural sophistication,
SOM produced full working drawings. Coordinating positions of 100,000
openings and holes in walls was a big challenge. With...high-strength
concrete, you cant drill it or just cut it, says Tomich.
Hyder, in the Gulf for over 20 years, was
hired because SOM has no local presence. Hyder has 60 of its 350
people in the area monitoring the burj. With 200 design submittals
a week, 40 of its staff concentrate on detail design issues only.
Hyder also handled foundation design.
Construction began late in 2003, with a 15-m-deep
basement excavation through sand and brackish water. In January
2004, following pile tests at up to 6,000 tonnes, workers began
installing more than 190 skin-friction piles, 1.5 m in diameter,
down to a 50 m depth.
Germanys
Bauer Spezialtiefbau with Middle East Foundations (UAE) handled
piling under a $15-million contract.
A switch to polymer, not bentonite, to support
the bores improved skin friction, reducing the required pile length
from 55 m to 49.5 m. That saved 15% on costs, says Turners
Bradford. Polymer also avoided increasing environmental concerns
over bentonite disposal.
Starting in April 2004, Australian-owned Nasa
Multiplex followed piling by casting the 18,000 cu m of concrete
for the 3.7-m-deep mat. Most of the underground structures are in
groundwater, which is unusually rich in chlorides and sulphates,
threatening to attack the steel and concrete respectively. With
a 100-year design life, the piles and mat foundation concrete has
epoxy-coated rebar and cathodic protection.
For the tower itself, Emaar selected a single
main contractor. Subcontractors are building specialty systems,
such as the curtain wall, building infrastructure systems and fit-outs.
The 47-month main contract, initiated in January
2005, went to a joint venture led by South Koreas Samsung
Corp. Samsung had helped build Malaysias Petronas Towers,
the worlds tallest until 2005.
 |
 |
| Kim |
The joint venture bid against six teams before
reaching a shortlist of two. It won on technical merit, though its
price was higher, says Kyung-Jun Kim, Samsungs vice president
and project director. Prices were very close, adds Bradford.
Since the Petronas towers, we have a
special team for high- rise, says Kim, who worked on the Malaysian
project. Samsungs partners, Arabtec Construction LLC and the
local unit of Belgiums Besix Group, bring experience of local
conditions and major projects to the team, he adds.
With Dubais explosive growth in construction,
Samsung was soon surprised by problems securing quality labor. Four
to five years ago it was easy, says Kim. For the tower, we
had to train them [on] new systems. It was very hard. Engineers
and supervisors are no easier to find, he adds.
 |
 |
| Photo:
MichaelGoodman/ENR |
This fall, the joint ventures labor
force reached over 2,500, working three shifts around the clock,
seven days a week. The crew is set to approach 6,000 at next years
peak, says Kim.
To ease construction, Kim early on asked for
their the highly congested reinforced concrete outrigger design
to be replaced with easier-to-build structural steel. Outriggers
now each contain 24 tonnes of 4-cm-thick, double steel plate which
is around 1 m deep.
Some 2,500 tonnes of hydraulically powered
climbing formwork for core and walls, from Austrias Doka Schalungstechnik
GmbH, is the joint ventures key construction tool. We
had to have a good system to account for all the changes,
says Kim.
 |
 |
Self-climbing
formwork is used for concrete walls.
Photo: MichaelGoodman/ENR |
Facing record-breaking pumping heights, the
contractor ran tests on pipes zigzagging over the ground. We
are going to pump it [about] 550 m. That requires extremely sophisticated
concrete design, says Turners Bradford.
Universal Concrete Products Ltd. Co. (Unimix)
LLC is supplying all the concrete and delivering it, mainly with
two super high-pressure pumps from Germanys Putzmeister A.G.
Raising wall-size rebar panels is the main
task of the towers three large Australian-made Favco hydraulic
luffing jib cranes. We had these machines and we discussed
(modifications) with Favco, says Kim.
For such heights, the drums needed designing
for 800 m of wire. Fourteen high-speed hoists from Czech supplier
Pega Hoists Ltd. transport people, cladding and other items.
The joint ventures learning curve started
at a concrete casting rate of one floor in seven days, accelerating
to the current three days some 50 floors up, says Kim. In summer,
pumping is possible only after 7 p.m., when temperatures fall below
the 40°C threshold. The tower is due to reach level 100 by this
years end and top off concrete, at floor 156, by next October.
First, workers cast the six-sided central
core. Wing walls and their slabs follow several floors behind, using
the self-climbers for the walls and a panel form system for the
slabs. Nose columns at the wing tips come next, with
their slabs, using circular steel forms for columns and a panel
form system for slabs.
The tower has 140,000 sq m of cladding. The
system consists of reflective glass in aluminum and stainless steel
spandrel panels with vertical tubular fins of stainless steel.
Installation of the curtain wall became troublesome
when the Swiss-based contractor Schmidlin A.G. went bankrupt early
this year. Its local operations were then saved by Arab investors.
Curtain wall installation just began. Schmidlins
problems caused a few months delay, says Kim.
They will operate two shifts to recover, he adds, forecasting
no adverse effects on the overall schedule.
The main hold-up now is in fitting out the
classy Armani Hotel Dubai, filling the towers lower quarter.
Giorgio Armani, whose company is responsible for the hotels
styling, seems less at home with high-rise than with haute couture.
Otherwise, Turners schedule for the
whole project, planned over three years ago, still holds. We
are actually slightly ahead, says Bradford.
|