|
Sharing
High-Tech Tools Creates Rocky Mountain High
Denver's
Unfathomable Form Brought in on Time and on Budget
5/15/2006
By
Nadine M. Post

 |
 |
| Spirit
of Collaboration. Architect Libeskind (left), client
Sharp support cooperation, no confrontation, on tough job. (Images
courtesy of Studio Daniel Libeskind LLC, left, DAM, top center,
and M.A. Mortenson Co., right) |
Another starchitect. Another unfathomable
form. Another potential money sinkhole. On the surface, architect
Daniel Libeskind's Denver Art Museum addition, a 146,000-sq-ft titanium-skinned
"geode," had all the ingredients for disaster. Except
in the eyes of M.A. Mortenson Co., which had recently cut its teethor
been through the meat grinderon the monarch of all description-defying
U.S. architectural icons, Los Angeles' Walt Disney Concert Hall.
Instead of running scared, Mortenson salivated at the prospect of
turning the agonies of Disney into the ecstacy of DAM. It landed
the $70-million job in August 2001.
By all reports, Mortenson has succeeded at
DAM, despite the job's geometric complexity. "It's been a great
project," says Lewis I. Sharp, the museum's director. "Having
just come off Disney was a big plus for Mortenson," he says.
"Rather than being frightened by the new technology, Mortenson
knew it could be the means to pull this off."
Sharp reports that, as first contracted with
the city, DAM is "on budget and on schedule." Substantial
completion is set for August. Opening day is Oct. 7.
Though the city owns the building, the private
museum, under a contract to the city, is really the client. DAM's
expansion, including Libeskind's Frederic C. Hamilton Building,
is financed by $62.5 million in city bonds and $28 million in private
funds.
 |
 |
 |
|
Virtual Steel Work. 3D digital
model for leaning structure included falsework, temporary steel,
rigging frames and crane locations. (Rendering courtesy of Fred
J. Fuhrmeister/Time Frame Photography, Photo courtesy of LPR)
|
 |
Inspired by the Rocky Mountains while flying
into Denver for his job interview, Libeskind started sketching the
building on the back of his boarding pass. The sculptural addition,
likened to a piece of origami for its many folds, angles and prows,
will house special exhibits and galleries of modern and contemporary
art, architecture, design and graphics. The five-level form is a
series of spaces defined by nonorthogonal planar walls. There is
little repetition and no typical floor.
DAM was the first public project in Denver
to take advantage of a change in city rules, pushed by contractors
and approved by the City Council in May 2001, that allows alternative
project delivery systems, including construction management-general
contracting, design-build and program management.
Studio Daniel Libeskind, New York City, was
selected in July 2000. Libeskind then picked the local Davis Partnership
as its joint-venture partner. Mortenson is the CM-GC, under a guaranteed-maximum-price
contract.
The original construction schedule called
for a 2004 completion. But among other things, an expanded scope
and resequencing of related projects, including a parking structure,
delayed the addition.
The role of CM and the contract award two
years before groundbreaking gave Mortenson leave to form a strategy
that included a preconstruction phasestarted in February 2002and
computer-aided communication, coordination and construction. Mortenson
pushed the sharing of three-dimensional (3D) electronic models between
design and construction teams. Trust has replaced early suspicion,
say sources. Collaboration, not confrontation is the job's mantra.
A "spirit of resolving problems" was set early in the
game by the client, says Tim Walsh, the vice president in charge
of the job in Mortenson's Denver office.
"The process was different from the traditional
linear process," says J.R. Barker, project engineer with Structural
Consultants Inc., the job's Denver-based steel-connection designer.
"Once a week, Mortenson brought the entire design and construction
team together and let them influence each other's lives," he
says. "Decisions were based on what was best for the project,
not for an individual."
The steel construction team agrees. "Everybody
was scared to death of this project going in, but preplanning made
things work," says Rocky Turner, president of Loveland, Colo.-based
LPR Construction Co., the steel erector.
Cooperation is one of the main things that
made this job different, adds Mark Zimmerman, president of local
steel subcontractor, Zimmerman Metals Inc.
 |
 |
| Teamwork.
Mortenson, with leader Walsh (right), relied on preconsruction
phase to work on constructibility issues with design team. (Phot
courtesy of M.A. Mortenson Co.) |
"It proved to be a fantastic job for
us," says Hugh Dobbie, president of steel detailer Dowco Consultants
Ltd., Burnaby, British Columbia.
Even the architect gets stroked. "Libeskind's
energy and passion inspired the team," says Walsh. Unlike some
starchitects, "he goes out and mixes it up with the workers."
Libeskind, in turn, calls the workers, "heroes."
Though not computer-literate himself, he values technology. "I
could have designed the museum without computers but it could never
have been built on time and on budget," he says.
Blurred lines between design and construction
phases and high-tech aids aside, 2D construction documents still rule.
The design consultants 3D design models were given to the contractor
for use without warranty, as a geometric control. This was done in
parallel with 2D documents. It was a big risk for the designers, says
Shannon Rogers, Mortensons model manager.
Though techno-soothsayers predict the coming
of a single master digital model, for this job there was still one
on the design side and one on the construction side. The architect
and the CM each needed a full-time model keeper. One of the tasks
was to coordinate with each other to keep the models in sync.
Mortensons 3D digital model, built from design-team
models, included steel, concrete, ductwork, piping, conduit, fire
sprinklers, scaffolds, temporary steel, falsework, crane locations,
even rigging frames for steel lifts. It was used during construction
for development and coordination of shop drawings, generated in
2D for field use. Mortensons 4D model, which added the element of
time, was used for visualization and construction sequencingfor
virtual prebuilding as a way to educate subs and anticipate and
eliminate field problems.
Success hinged on getting the structural engineers
digital wire-frame model to the steel detailer to create a solid
model. At first, that did not sit well with the architect. I dont
think any of us [on the design team] going in knew we were going
down that roadgiving the contractor our 3D models, says Maria Cole,
Daviss associate on DAM.
Believer
Skeptical at first, Davis is now a believer
in sharing. Having the contractor on board early, studying the architects
3D model and physical scale models, and offering suggestions on
constructibility, allows you to imagine spaces beyond what were
capable of in 2D, Cole says.
Sharing digital models still puts challenges
on design, says the architect. Certain things, lost in translation,
need to be redrawn. Working with the model is cumbersome and time-consuming
because it is information-intensive.
For the rest of the consultants, the process
differed from the norm in that full 3D models were provided by the
architect and the contractual deliverable included 3D versions of
the design, says Erin McConahey, an associate principal in Arups Los
Angeles office.
Arup,
also the mechanical structural consultant, extracted valuable information
from the architects volumetric digital models, including edge and
top of flange and centerline of steel. Thanks to 3D, the firm was
able to coordinate the frame, ductwork and piping, minimizing coordination-related
requests for information. Every beam penetration was factory-cut
and its location known during the design phase, says McConahey.
On the business side, Mortenson learned on
Disneythe hard waythat to make the process work it is imperative
to develop specific, detailed subcontractor contract language on
generation and hand-off of electronic data. But all the models in
the world wont help if people in the field arent familiar with the
system. Its a learning process, says Walsh.
Biggest Bear
The
steel frame was the biggest bear on the project. Mortenson had a process
where issues were identified in a pre-detailing request and resolved
through Web meetings and other correspondence. That, combined with
use of the 3D digital model, prevented 1,200 collisions of steel elements
and sped steel erection to the finish line three months early. Mortenson
then gave nearly $400,000 back to the owner. The frame consists of
mostly sloping columns with diagonal braces to resist lateral loads.
There are about 40 different slopes. Perimeter walls lean outward
from the horizontal 40 to 84. The only vertical elements other than
some interior columns are elevator shafts.
The inclined walls generate permanent lateral
loads throughout the floor system, which equate to similar design
loads in a seismic zone, says Atila Zekioglu, an Arup principal.
Horizontal beams, strategically placed, counteract instability of
the inclines by acting like a tension tie.
Floor plates and individual roof planes are
used as diaphragms to distribute lateral loads, with extensive use
of drag-strut connections to distribute concentrated horizontal
forces into the composite concrete-on-metal-deck diaphragm and back
into perimeter walls and interior braced planes. Additional deck
bracing and steel plates are under the deck in locations of high
plane shear forces. Inclined walls are supported at ground level
on vertical planes, where shear forces are transferred to reinforced
concrete walls. Interior walls are supported on steel bracing in
the vertical plane which in turn takes shear forces to caisson foundations.
Precambering was required on some joints in
the frames vertical and horizontal directions to accommodate up
to 3 in. of deflection when shoring was removed.
 |
 |
| In
Time. 4D solid model, which even included concrete, "prebuilt"
the job from bottom to top. (Image courtesy of M.A. Mortenson
Co.) |
Because of the unstable geometry, the erection
sequence took precedence during preconstruction meetings. Sources
say that when LPR spoke, everyoneeven the structural engineerlistened.
LPR created an 18-sequence erection plan for
the 2,740 tons of steel. The plan, which included shoring, rigging
design and crane reach drawings, was detailed in 3D, including step-by-step
sequencing. Use of the 3D model in the office and the field was
paramount to the projects success, says Curtis Mayes, LPRs director
of preconstruction and engineering.
One of the toughest sequences was the erratic
13th, under the roofline. LPR could not figure out a reasonable
way to shore the sequence, so it had to figure out how to stabilize
members temporarily until other pieces were in place. Mayes used
more than 50 3D slides to teach the sequence to the team.
 |
+ click image
to view full diagram

|
| Hollow
Geode. No two floors of hte five-level museum have the
same footprint. (Image courtesy of DAM/Miller Hare) |
Coordinate geometry made alignment difficult.
X-Y-Z survey coordinates were incorporated into the 3D model. All
primary columns, sloping and vertical, were detailed and fabricated
with shop-drilled control holes designed to hold a surveyors prism
at a theoretical spot in space. A second survey location was fabricated
into the member using a center-punch mark to locate and install
a reflective target on the surface of the column. High-tech transits
were programmed with the coordinates.
Zimmerman fabricated oversized bolt holes
to allow the erector to use full-size fit-up pins. This was key
to the fit-up, allowing easy field adjustment for imperfections
in plate alignment, says LPR.
During design, Arup checked the structure
and the mechanical service for clashes. The challenge was to place
ductwork in the walls to minimize shaft space. The museum also wanted
to minimize water piping in the art galleries. That meant home-running
ductwork to central mechanical rooms containing air handlers. That
was difficult because risers sloped every which way.
 |
 |
 |
|
Inclined. Museum walls lean at
about 40 different angles, making work more labor-intensive.
(Images courtesy of M.A. Mortenson) |
 |
Arup laid out every duct run in 3D. When a
run hit a steel member, a beam penetration was indicated on shop
drawings and cut out during fabrication. Arup has already used 3D
mechanical layouts on three other projects. Mostly it is used for
mechanical rooms and tight ceiling-void pinch-points, says McConahey.
For the Loveland, Colo., office of U.S. Engineering
Co., the mechanical subcontractor with a $6.3-million contract,
the interface with other subs during Mortensons preconstruction
phase was novel and helpful, as was the 3D solid model.
The jobs many bends were much easier to visualize
in 3D. We used more offsets than we ever could have imagined and
more support steel to support plumbing, says Daniel Kern, U.S. Engineerings
project manager.
On the air side, it was also difficult to
follow the planes.Nothing was square so we couldnt lay out normally,
he says.
U.S. Engineering got involved in June 2003,
replacing the original mechanical sub that had financial woes. We
had to jump in quickly on the 3D portion, says Kern.
It was a learning process. Despite all the
efforts, Kern says there were several collisions on each floor.
 |
 |
 |
| Coordinated.
Engineer ordered beam penetrations for duct runs. (Image courtesy
of DAM/Miller Hare) |
The electrical conduit followed. To lay out
systems, Dynalectric Co. of Colorado, which has a $5.4-million contract,
coordinated with mechanical and sprinkler contractors through Mortenson.
The coordination was incredibly critical to locate their equipment,
our equipment and how the systems run, says Craig W. Clark, president
of the Lakewood, Colo.-based firm. I wouldnt say it was perfect
but it worked quite well, he adds.
Clark says that with so many wall inclines,
getting access to the top of each for lighting fixtures was difficult.
Workers had to use mechanical lifts with arms, instead of ladders.
The installation was about 40% more labor-intensive compared to
a typical building. Its an OK job. I wouldnt say we got rich, he
says.
Mortenson is already basking in the glow of
its accomplishment, especially compared with Disney, although the
concert hall was twice as big and in a high seismic zone. But Disney
had 10,000 requests for information; DAM has 1,300. Disney, which
opened in late 2003, has an outstanding claim, rumored close to
settlement, of about $40 million. DAM has no claims pending or expected.
That said, without Disney there may not have
been a DAM for Mortenson.
|