|
At NOAA's
Satellite Operations Facility, Protecting the Environment is Mission
Critical
11/2006
By
Nadav Malin

 |

Click here to view a slide show; Photo
© Maxwell Mackenzie |
|
KEY PARAMETERS
Suitland, Maryland (Middle Potomac watershed)
PROJECT SIZ E: 208,000 ft2 /
19,320 m2
COMPLETED: May 2006
COST: $54 Million
ANNUAL ENERGY USE: 60 kBtu/ft2
(690 MJ/m2)19% reduction from base case
ANNUAL CARBON FOOTPRINT (PREDICTED):
18 lbs. CO2/ft2 (90 kg CO2/m2)
PROGRAM: Offices, satellite
control rooms, computer rooms, conference rooms, exercise
facility, cafe.
DATA click to View larger
 |
 |
 |
| Heating/Cooling |
Temp./Dew Point |
Sky Conditions |
NOAA TEAM
OWNER: General Services Administration
ARCHITECT: Baird Sampson Neuert
architects
COMMISSIONING AGENT: General
Services Administration
ENGINEER Einhorn Yaffee Prescott
(MEP); Arup (structural, concept design); Cagley and Associates
(structural); IBE Consulting Engineers (mechanical); EYP Mission
Critical Facilities (electrical); A. Morton Thomas & Associates
(civil)
LANDSCAPE ARCHITECT: EDAW
LIGHTING: Horton Lees Brogden
ACOUSTICS: Shen Milsom &
Wilke
SECURITY: Ted Kesik
GENERAL CONTRACTOR: P.J. Dick
SOURCES
METAL/GLASS CURTAINWALL: PPG
Sungate 100 low-e clear insulating glass
LADDING: Swisspearl Carat, open
joint fiber cement board panel system over Bakor Air-Bloc
33 vapor-permeable air BARRIER :
Focal Point Groove compact fluorescent with integrated custom
acoustical panel. Acoustical panel uses Echo Eliminator Bonded
Acoustical Pad
LOW-SLOPE ROOFING : Bakor 790-11
hot-fluid-applied rubberized asphalt membrane with 25% post-consumer
recycled content is the waterproofing layer for green roof
and non-green roof areas.
CARPET: Milliken Raffia Tex
carpet tiles
|
Photographs from the national oceanic and
atmospheric Administrations (NOAA) satellitesviews of
the earth and its weather patterns from abovepervade our media-rich
culture. With this established public face, NOAA officials saw little
need for a signature building by a big name architect. If it provided
the tools they needed to control their satellites, a ho-hum building
would do just fine, thank you. But the U.S. General Services Administration
(GSA), which procures and manages facilities for most federal agencies,
had other plans, and enrolled the project in its Design Excellence
Program. One area in which the two agencies did agree was that the
building should be green: GSA had just begun mandating a minimum
LEED Silver rating when the project was announced, and NOAA sees
itself as an environmental agency. Our mission is environmental
stewardship, says Paul Pegnato, NOAAs project manager
for the facility. Our building projects that stewardship.
Led by Thom Mayne (now a Pritzker Prize laureate),
the joint venture of Morphosis and Einhorn Yaffee Prescott (EYP)
developed a scheme based on several underlying goals. The first
goal was to conceal as much of the buildings required program
space so as to lessen the visual impact of its volume on the site,
which abuts residential neighborhoods in a Washington, D.C., suburb.
The second was to put the majority of the employees on a single
floor plate, to avoid the risk of departments getting broken up
on separate floors. And the third was to provide an elegant, integrated
solution that would accommodate the satellites, the people, and
the technology that connects them.
These goals led to the unexpected design solution
that features satellite dishes on the roof of a windowless rectangular
box, dubbed the bar, that houses the control rooms,
while most of the employees work below grade in a cavernous, disk-shaped
zone punctuated by light wells and skylights. A vegetated roof on
the shallow dome over the main work space merges seamlessly into
the landscape on the north, making most of the buildings volume
disappear from view. A glazed wall on the south, where the natural
grade is lower due to the slope of the site, introduces light and
views. Parking and mechanical rooms are farther below grade, underneath
the main work space.
While Morphosis led the overall design, EYP
took the lead on the green strategies. EYP project architect Doug
Gehley (now with SmithGroup) says beyond the requirement for LEED
Silver certification, little direction came from the agencies regarding
environmental priorities. The client left it wide open,
he says. Our goal was to sit in the meetings and watch for
opportunities in the design as it started to develop. Once
environmental opportunities were identified, teams that included
designers from both Morphosis and EYP, and client representatives
from NOAA and GSA, developed the solutions.
The mechanical engineers were charged with
developing three designs for the buildings systems. Of these,
a system based on under-floor air delivery was chosen as the most
effective way to provide comfort and fresh air to the occupants
in a space with ceilings up to 28 feet high. Displacement ventilation
with under-floor air provides other efficiency gainsincluding
reducing the need to chill air for coolingbecause it isnt
being mixed with air that has already been in the space. Fan energy
is reduced because the air is delivered at low speed and pressure.
These benefits, combined with high-performance chillers and other
measures, provide a predicted energy cost savings of 28 percent
over the ASHRAE 90.1-1999 baseline. The under-floor air system also
provides a level of individual control that would be tough for another
system to match in an open floor plan.
The unexpected design features satellite
dishes on the roofdubbed the barof a windowless
rectangular box.
Lighting the large, open work space was a
challenge, according to Teal Brogden, senior principal at Horton
Lees Brogden Lighting Design. One constraint was the mandate from
GSA to have ambient lighting that provides at least 30 foot-candles
of illumination on the work surfaces, even though individual task
lighting was also available. In some work situations we might
take the ambient light levels down to 15 or 20 foot-candles,
says Brogden. At the same time, the glazed wall on the south and
the large light-wells create bright zones that had to be balanced
to avoid uncomfortable contrasts. Based on lighting models, tubular
skylights were added to enhance the daylight distribution, but filling
the space with the number of skylights that it would take to light
with daylight was not in the original budget, notes Brogden.
Instead, daylight was meant to provide pools of visual interest
and relief.
Another element that wasnt feasible
because of lack of funding was operable shading devices on the vertical
glass. Instead, the designers installed a fixed black scrim on the
upper sections of the glazing to control glare, a solution that
cuts down on the available daylight even when it is desired. GSA
is considering removing that scrim, at least from the north and
west sides, where it isnt needed to control direct sunlight,
but no final decision has yet been reached. We had suggested
that they wait through the summer before they decide, says
David Rindlaub, project architect with Morphosis. The risk of direct
sunlight affecting workstations is mitigated somewhat by the high
partitions in the systems furniture that GSA selected. While these
partitions increase the amount of privacy in the individual cubicles,
they also create a maze-like effect, and reduce the sense of spaciousness.
The combination of unusual form, high technology,
and green measures made construction administration and commissioning
a challenge. There were some things that the contractor hadnt
done before, notes Steve Baumgartner, who managed the commissioning
process for EYP. In particular, keeping the under-floor plenum clean
during construction was difficult. The technology challenge emerged
when the engineers needed to commission the control room with actual
electrical and thermal loads in place. They wouldnt
move the equipment in until it was tested, but we couldnt
test without the loads in the spaces, says Baumgartner. Ultimately
they found ways to simulate the loads that the equipment was expected
to produce.
Yet another challenge on this project was
the relatively high level of turnover among members of the design
team. EYPs Gehley feels that this risk of turnover highlights
the value of design firms that have enough depth in terms of green
expertise and LEED-accredited professionals to carry a project forward
when one person leaves.
While certification wasnt completed
by press time, there is optimism that the project will exceed GSAs
LEED Silver requirement and achieve Gold. Its too soon to
judge how well the satellite control systems will work out, since
the high-tech, mission-critical functions are still being fine-tuned.
The design surely succeeds in fulfilling the goal of creating a
provocative, iconic form. Some people had a hard time, because
it wasnt the conventional building they thought they were
going to get, says Gehley. Among those who struggled through
the process was NOAAs Pegnato, who still isnt convinced
of the value of the buildings drama. Knowing what we
know now, we could have tweaked the form to provide a bit higher
level of function, he suggests. But he has no reservations
about the green agenda. Relative to the green building, I
would retain all aspects of the project.
|