McGraw-Hill Construction
   subscriptions  •   advertise  •   careers  •   contact us  •   my account  
 



email a friend  |  printer friendly version
Transportation

Suspension Span Defies Tradition


(enr.com 12/24/01)

By David B. Rosenbaum

DISTINCTIVE New Carquinez Bridge (top) next to older pair, has slender concrete towers and slim box girder (above). (Photo and graphic courtesy of Parsons Inc.)

Commuters heading east from San Francisco on Interstate 80 might not find the nation's first new suspension bridge in a generation comparable to the Golden Gate Bridge in terms of remarkable span length, tower heights or Art Deco details. But the new Carquinez Bridge will sport its own distinctive features.

Under a $188-million contract bid nearly two years ago–at the time the largest ever let by the California Dept. of Transportation–the new bridge has concrete instead of steel towers, which saved at least 50% on construction. With both 120-m-tall towers erected, 60% of the contract dollars spent and 42% of the schedule used up, the bridge is rising in contrast to two nearby crossings.

It will stand out even more after cable spinning begins next November, followed in April 2003 with delivery of 24 prefabricated segments to be lifted and assembled into an unusual 1,056-m-long four-lane superstructure–the first orthotropic steel box girder for a major U.S. suspension bridge. Fabricating 12.7 million kilograms of steel for the $30-million box girder in Japan saved 30% off the budget, the construction team estimates. The contractor, a 70:30 joint venture of FCI Constructors Inc. and Cleveland Bridge California Inc., expects to save another $1 million by using strand jacks instead of a 1,000-ton gantry to lift the 50-m-long segments.

Scheduled to open by November 2003, the new bridge will parallel two spans–one built in 1927 and slated for demolition, the other built in 1958 and newly retrofitted for earthquakes. Both older spans hang from steel trusses and three towers; the middle towers sit in the shipping channel of the Sacramento River 20 miles east of San Francisco. Caltrans had considered a third tower for the new bridge as well, to support a cantilever truss, concrete arch or cable stays. But it wanted to minimize shipping risks and foundation costs. For economy's sake, the two-tower decision dictated the design of a 728-m-long main span for the first major U.S. suspension bridge since the Chesapeake Bay Bridge in 1973.

The new Carquinez Bridge incorporates advancements in suspension bridges made since then in Europe and Asia, says Thomas Spoth, the bridge's design manager in the New York City office of Parsons Transportation Group Inc. For one, the design features a shallow orthotropic steel box girder, just 3 m deep and trapezoidal in cross section. Nosings at either side of the 29-m width allow wind to flow over, so the girder remains flutterless at wind speeds of less than 260 km/hr. By comparison, a wind just one-quarter as strong collapsed the first Tacoma Narrows Bridge in 1940.


REPLACEMENT Rendering shows new bridge with older of adjacent two removed. (Photo courtesy of Parsons Inc.)

Most suspension bridges contain open trusses. A proposal for a new Tacoma Narrows Bridge, for which Spoth also managed the design, calls for a truss to allow for a future lower deck. But using a truss requires heavier cables to support the extra weight of floor framing. With a lightweight box girder, a design team that includes OPAC Consulting Engineers, San Francisco, held down the Carquinez Bridge's suspension cables to a diameter of 512 mm. In a first for a U.S. suspension bridge, Spoth says, the design makes specific allowances for the loss of any one of the vertical ropes that support the superstructure from the main cables.

According to Spoth, using large-diameter drilled shaft foundations for the towers instead of concrete caissons is also rarely seen in U.S. bridges. In a quake, massive caissons tend to rock.

The 3-m-dia concrete shafts, with steel shells about 45 m long, are socketed as much as an additional 35 m into rock. Because rock under the south tower lacked the anticipated strength, a $10-million change order and a 355-day extension of the original 1,200-day schedule was needed, says Curtis Weltz, project manager for the FCI-Cleveland Bridge joint venture in Crockett, Calif. The team started work in February 2000 and intends to avoid paying liquidated damages of $50,000 per day after the first 1,000 days, "so all the decisions are schedule driven," Weltz says (ENR 1/31/00 p. 24).





Subscribe to ENR and get unlimited access to ENR.com

sponsors

 |   |   |   |   | 
2008 © The McGraw-Hill Companies, Inc.
All Rights Reserved