McGraw-Hill Construction
   subscriptions  •   advertise  •   careers  •   contact us  •   my account  
 



email a friend  |  printer friendly version
Buildings

Congested Site at Chicago's Millennium Park Calls for Delicate Movement of Machinery

(enr.construction.com - 02/09/04 issue)

ByTudor Hampton

TANGLED Trades finishing music pavilion fight for aerial real estate.

A complex project without logistical challenges is like a rock concert without dramatic flair. Likewise, the story of Millennium Park’s amphitheater in Chicago is a potent reminder of how contractors faced with the daily problem of a congested and ever-changing urban site must carefully select and plan equipment to make it work.

Communication among trades at Millennium Park has been critical for safety at a site that has been packed with machines. The 30,000 sq-ft apron area facing the site’s Frank O. Gehry-designed music pavilion has during construction hosted a cacophony of heavy equipment and materials needed to erect the amphitheater. Scheduled to open in July, its high-swooping, stainless-steel "ribbons" and adjacent open-air trellis are the park’s centerpiece (see p. 24).

advertisement

"I had 19 aerial lifts and three cranes on the job, all in the same [30,000-sq-ft] footprint," says Patrick R. Buck, project manager for Chicago-based Walsh Construction, general contractor responsible for building the music pavilion and surrounding 95,000-sq-ft seating area that comprise about five acres of the 24.5-acre park near Lake Michigan. He says that equipment utilization peaked last August, after erection of the structural steel above the stage was nearing completion.

In order to facilitate safe operations last summer, "the subs would have a 10-minute talk session every morning," says David J. Markovich, Walsh senior superintendent. "If one of the dominoes fell apart, it would wreak big havoc on the job," he adds. Site meetings now are being held twice a week.

To complicate matters, ground loading issues have restricted movement of equipment and materials. The pavilion and trellis bear on a concrete raft slab covering an active, 2,181-space, underground parking garage. "Site logistics and utilization were very difficult," says Wayne Anderson, Walsh’s senior project manager.

One innovative solution came from steel erector Danny’s Construction Co. Inc., Gary, Ind., which needed to position two crawler cranes without using added shoring to support the slab. The firm designed a steel cribbing system on which the two cranes could track from west to east as erectors placed the pavilion’s elevated steel elements.

REACH Steel erector’s 90-ton cribbing system bolsters lift cranes.

Built last February and struck in mid-September, the 90-ton "grillage" included five moveable "bays" of two, 29-ft-long girders and two, 30-ft-long stringer beams. The unit was able to distribute the weight of the two Manitowoc 999 275-ton lift cranes to the garage columns and down through the caissons, according to Dave Budzius, Danny’s project manager. "We’ve done similar things in the past, but more to provide additional bearing for the crane on less-than-desirable soil," he says.

The project has had no major equipment accidents to date. The team’s biggest challenge remains orchestrating the movements of subcontractors installing the pavilion’s stainless steel skin from 80 to 150-ft-tall aerial lifts. "If we didn’t have open communication, we would all be on top of each other," says Markovich.

(Photos courtesy of Walsh Construction)





Subscribe to ENR and get unlimited access to ENR.com

sponsors

 |   |   |   |   | 
2008 © The McGraw-Hill Companies, Inc.
All Rights Reserved